| | TUCSON ELECTRIC POWER - ASH HAUL ROAD Re-construction of 31,680 LF of haul road for 100 ton ash haul trucks, consisting of widening road way of various widths to a constant 60’ width, pulverization of existing chip sealed surface stabilizing with lime slurry and fly ash, re-compaction and grading placement, 3 compaction of 44,140 tons of aggregate base course 4” thick. Installation of a double chip sealed surface, grading ditches & slopes for drainage, reflective shoulder markers. Role: Western Grade filled the position of general contractor, self performing all earthwork, grading, compaction and installation of reflective shoulder markers, stabilization & chip seal surfacing work performed by subcontractors. Original Project Amount was $3,000,000.00 Original Contract Amount was $2,390,000.00 Completed Cost was: $2,197,507.50 Owner: Tucson Electric Company References: James Nelson Jr. PE T.E.P. 928-245-0798 or 928-337-7328 Skip Vaughan Contractor Administrator T.E.P. 928-245-2165 |
| | SNOW CREEK UNIT 1 A 97 lot residential sub division with 7200 LF of asphalt, earth work/sub grade and lime stabilization, paved roadways ribbon curb, sewer, water, electric, gas, telephone, cable & drainage system, ADOT turn lane at entrance, 3100 LF access entrance and all associated SWPPP & re-vegetation items. Role: Western Grade, LLC filled the position of general contractor completing all aspects of construction in house except paving which was subcontracted. Engineering by Tetra-tech. Original project amount was : $3,150,000.00 Original contract amount was : $2,484,903.00 Completed cost was : $2,554,903.00 Project Began: 1-25-06 Owner: Snowcreek Development, LLC References: Ron Belmor (Owner Rep) 928-532-0532 Office 928-521-1240 Cell Cory Frampton (owner) 602-228-9331 |
| | TORRE LAKES SUBDIVISION 79 lot residential subdivision with 3450 lf of asphalt paved roadway, earth work/sub grade prep, ribbon curb, dry utility installation, construction of 5 lakes with total volume of 11,000,000 gallons, roadway & lot drainage systems. Role: Western grade fill as the position of the general contractor, completing all aspects of construction in-house, except paving which was subcontracted, ADOT turn lane at entrance and all associated SWPPP and re-vegetation items. Engineering by Tetra-Tech. Original project amount: $6,500,000.00 Work contracted on time & materials basis: $2,282,295.73 Project Began: March 17, 2006 Owner Suntide West, LLC References: Scott Backes 928-242-8513 David Nothum 314-368-0101 |
![]() | SRP - Dry Lake Windfarm Description. Original Project Amount was $ Original Contract Amount was $ Completed Cost was: $ Owner: Salt River Project References: 928-000-0000 or 928-337-7328 Skip Vaughan Contractor Administrator T.E.P. 928-245-2165 |
| | ELK RIDGE APARTMENTS Original Project Amount was $120,000 Original Contract amount was $92,613 Completed Cost was $92,613 Apartment Complex ADOT Turn Lanes, Paving, Grading, Concrete curb, Drainage, Striping, Signage |
| | PINE BLUFFS Original Project Amount was $339,667.00 Original Contract amount was $339,667.00 Completed Cost was $339,667.00 35 Acres, 52 Lot Subdivision Paving, Grading, Concrete curb, Drainage |
WOODLAND HILLS SUBDIVISION Original Project Amount was $2,356,319.00 Original Contract amount was $2,153,598.00 Completed Cost was $2,154,989.00 100 Acres, 152 Lot Subdivision Paving, Grading, Concrete curb, Drainage, Underground Utilities | |
| | CREEKSIDE SUBDIVISION Original Project Amount was $965,000 Original Contract amount was $734,000 Completed Cost was $734,000 7.2 Acres, 41 Lot Subdivision Paving, Grading, Underground Utilities, Concrete curb, Drainage |
MAVERIK CONVENIENCE STORE & GAS STATION Original Project Amount was $622,232 Original Contract amount was $667,590 Completed Cost was $667,590 Convenience Store Hwy 60 / Hwy 77 Site Preparation, Underground Utilities, Fuel Tank Installations, Paving, Grading, Concrete curb & Sidewalks, Drainage | |
| EAGLE MOUNTAIN Original Project Amount was $280,000 Original Contract amount was $259,332 Completed Cost was $275,806 ADOT Turn Lanes, Paving, Grading, Concrete curb, Drainage | |
| SUMMIT TRAIL EXTENSION Original Project Amount was $692,825.00 Original Contract amount was $642,825.00 Completed Cost was $642,825.00 3500 LF New Road Construction Paving, Grading, Concrete curb, Drainage, Underground Utilities, Clearing & Grubbing | |
| SIERRA PINES UNIT 9 Original Project Amount was $763,276.00 Original Contract amount was $645,900.00 Completed Cost was $645,900.00 60 Acres, 80 Lots 3750 LF Road Paving, Grading, Concrete curb, Drainage | |
| SIERRA SPRINGS RANCH Original Project Amount was $932,000 Original Contract amount was $859,000 Completed Cost was $859,000 72 Acres, 51 Lot Subdivision Paving, Grading, Concrete curb, Drainage | |